A lot of things were done during Christmas break over at the house. The drywall is up and almost done. The rooms are really starting to come together. Jeff and I stopped by the house to check out the master closet. I'm already thinking of a million ways to organize every single inch of that space. The problem with the closet is I have no idea where I want to put the bars that hold the clothes and where all the shoes should go. We obviously want to maximize the space as best as possible and for me, I want lots of hanging space! This is what I have so far but I guess we'll see what the closet guy says. Maybe he has better ideas.
This week we should also see the siding go up so at least the outside of the house will be almost done, other than the stone. Once the drywall is done I'm assuming that's when all the fun stuff will start going in and when I'll have much more fun pictures to show.
1. Entryway from the front door
2. Entryway from living room
3. Kitchen; Pantry on right.
4. Pantry on the left, mudroom on the right
5. Living room from the kitchen
BUILDING TIMELINE:
Oct 8 (Day 1) - We signed our contract and everything is official!
Oct 9 (Day 2) - Expected ground breaking - delay with permit.
Oct 14 (Day 7) - Pick out front door (similar to this), interior doors, house molding, door knobs, and decking and siding.
Oct 15 (Day 8) - Fireplace
Oct 21 (Day 14) - Faucets, sinks, shower heads, toilets. Also garage door.
Oct 23 (Day 16) - Cabinetry for the whole house - knobs and handles
Nov 5 (Day 29) - Ground breaking - hole digging and laying some foundation.
Nov 13 (Day 37) - Outside brick
Nov 18 (Day 42) - Cabinet place again - Changed our minds of the kitchen cabinets!
Nov 19 (Day 43) - Chose lighting, sort of because that was pretty hard. Still have to finalize some choices.
Week of Nov 24 (Day 53) - Pour concrete base - framing basement - finalize light choices and custom island color, custom hood vent and misc faucets.
Week of Dec 8 (Day 68) - Finishing up the framing and starting the roof. Plywood mostly put up all around the house. It's starting to look like a house.
Week of Dec 15 (Day 75) - Framing complete and ready for siding. Roof almost finished. Electrical walk-through, still deciding on lights. Electrical rough-in and instal of fireplace. Tubs in bathrooms.
Week of Dec 22 (Day 82) - Inspections. Insulation and drywall will be up this week. Final interior finishes picks.
Oct 8 (Day 1) - We signed our contract and everything is official!
Oct 9 (Day 2) - Expected ground breaking - delay with permit.
Oct 14 (Day 7) - Pick out front door (similar to this), interior doors, house molding, door knobs, and decking and siding.
Oct 15 (Day 8) - Fireplace
Oct 21 (Day 14) - Faucets, sinks, shower heads, toilets. Also garage door.
Oct 23 (Day 16) - Cabinetry for the whole house - knobs and handles
Nov 5 (Day 29) - Ground breaking - hole digging and laying some foundation.
Nov 13 (Day 37) - Outside brick
Nov 18 (Day 42) - Cabinet place again - Changed our minds of the kitchen cabinets!
Nov 19 (Day 43) - Chose lighting, sort of because that was pretty hard. Still have to finalize some choices.
Week of Nov 24 (Day 53) - Pour concrete base - framing basement - finalize light choices and custom island color, custom hood vent and misc faucets.
Week of Dec 8 (Day 68) - Finishing up the framing and starting the roof. Plywood mostly put up all around the house. It's starting to look like a house.
Week of Dec 15 (Day 75) - Framing complete and ready for siding. Roof almost finished. Electrical walk-through, still deciding on lights. Electrical rough-in and instal of fireplace. Tubs in bathrooms.
Week of Dec 22 (Day 82) - Inspections. Insulation and drywall will be up this week. Final interior finishes picks.
Week of Jan 5 (Day 96) - Siding, finishing drywall