The kitchen island was probably the most scary choice I've made so far in this house.  It's bold & unexpected and because of that, super scary.  We picked the color on a little paint chip so we kind of just hoped once it was on the island it would be everything we hoped, and it is!  What a relief! I cannot wait to see what the finished kitchen will look like with this little beauty inside.


I also took a couple more progress pictures. Nothing super crazy but still exciting seeing all the little pieces come together so quick.  Since the trim is all done, this week they'll start touching up the drywall and starting to paint.  It'll be so nice to see some color on the wall.  (and again, we hope we made the right choice when picking out colors from a little paint chip!)


BUILDING TIMELINE:
Oct 8 (Day 1) - We signed our contract and everything is official!
Oct 9 (Day 2) - Expected ground breaking - delay with permit.
Oct 14 (Day 7) - Pick out front door (similar to this), interior doors, house molding, door knobs, and decking and siding.
Oct 15 (Day 8) - Fireplace picked
Oct 21 (Day 14) - Faucets, sinks, shower heads, toilets.  Also garage door.
Oct 23 (Day 16) - Cabinetry for the whole house - knobs and handles
Nov 5 (Day 29) - Ground breaking - hole digging and laying some foundation.
Nov 13 (Day 37) - Outside brick picked
Nov 18 (Day 42) - Cabinet place again - Changed our minds of the kitchen cabinets!
Nov 19 (Day 43) - Chose lighting, sort of because that was pretty hard. Still have to finalize some choices.
Week of Nov 24 (Day 53) - Pour concrete base - framing basement - finalize light choices and custom island color, custom hood vent and misc faucets.
Week of Dec 8 (Day 68) - Finishing up the framing and starting the roof. Plywood mostly put up all around the house. It's starting to look like a house.
Week of Dec 15 (Day 75) - Framing complete and ready for siding. Roof almost finished. Electrical walk-through, still deciding on lights.  Electrical rough-in and instal of fireplace. Tubs in bathrooms.
Week of Dec 22 (Day 82) - Inspections. Insulation and drywall will be up this week. Final interior finishes picks.
Week of Jan 5 (Day 96) - Siding, finishing drywall.
Week of Jan 19 (Day 110) - Cabinets being delivered, Trim going up
Week of Jan 26 (Day 117) - Cabinetry installed - Custom cabinetry made and installed - continue trim
Week of Feb 2 (Day 124) - Finish trim - start painting