Last week they finally installed our hood and the carpenter our contractor hired did an amazing job. It was everything I asked, and gave us the feeling I was hoping for; fanci (er), but not too fancy. Still casual, but with a little class. It really pulled the kitchen all together, and other than a good cleaning, this place is pretty much ready to be cooked in.
And another credit to the carpenter for making some pretty corbels for our island. I drew him a picture and he delivered. That's what I like to see. =)
BUILDING TIMELINE:
Oct 8 (Day 1) - We signed our contract and everything is official!Oct 9 (Day 2) - Expected ground breaking - delay with permit.
Oct 14 (Day 7) - Pick out front door (similar to this), interior doors, house molding, door knobs, and decking and siding.
Oct 15 (Day 8) - Fireplace picked
Oct 21 (Day 14) - Faucets, sinks, shower heads, toilets. Also garage door.
Oct 23 (Day 16) - Cabinetry for the whole house - knobs and handles
Nov 5 (Day 29) - Ground breaking - hole digging and laying some foundation.
Nov 13 (Day 37) - Outside brick picked
Nov 18 (Day 42) - Cabinet place again - Changed our minds of the kitchen cabinets!
Nov 19 (Day 43) - Chose lighting, sort of because that was pretty hard. Still have to finalize some choices.
Week of Nov 24 (Day 53) - Pour concrete base - framing basement - finalize light choices and custom island color, custom hood vent and misc faucets.
Week of Dec 8 (Day 68) - Finishing up the framing and starting the roof. Plywood mostly put up all around the house. It's starting to look like a house.
Week of Dec 15 (Day 75) - Framing complete and ready for siding. Roof almost finished. Electrical walk-through, still deciding on lights. Electrical rough-in and instal of fireplace. Tubs in bathrooms.
Week of Dec 22 (Day 82) - Inspections. Insulation and drywall will be up this week. Final interior finishes picks.
Week of Jan 5 (Day 96) - Siding, finishing drywall.
Week of Jan 19 (Day 110) - Cabinets being delivered, Trim going up
Week of Jan 26 (Day 117) - Cabinetry installed - Custom cabinetry made and installed - continue trim
Week of Feb 2 (Day 124) - Finish trim - start painting
Week of Feb 16 (Day 138) - Continue with paint. Counter-tops installed in kitchen, bathrooms and kitchenette downstairs. Install tile backsplash in kitchen and laundry room. Install tile in master bath
shower and backsplash. Install lighting.
Week of March 2 (Day 152) - Carpet install. Trim and hardware finish. Faucets & sinks.
Week of March 9 (Day 159) - Slow week at the house. Just a couple of touch ups here and there.
Week of March 16 (Day 166) - Concrete in the porch and garage, Starting the deck. Starting master shower re-do since they didn't quite hit the mark the first time. Touch ups around the house. Deep cleaning and paint touch ups.